I have available budget 60,00,000/- against a wbs as seen from S_ALR_87013558 and the system status of wbs is ISBD. Here I am thinking of CJEN->CJBN and then program RKANBU01/RKACOR04. Am I correct here?
Now, I checked the same in DEV client with -ve available budget against a wbs and system status ISBD for the wbs. I ran CJEN->CJBN and then program RKANBU01, what i see now is that Budget overall and Actual Overall column are showing "0" values in S_ALR_87013558. please suggest what has gone wrong.
Thanks & Regards
Ankur
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In CJ31 Goto Extras > Availability control > Analysis
Then in the command line enter "=SUM" and press enter.
Analyse the availability control data here.
Hope you are aware that Budget availability control and S_ALR-...558 report may show different values. Budget control actually happens through availability control prog based on which the ISBD status is set if there is insufficient budget.
CJEN is for cost reconstruction.
You may also have to execute CJBN to reconstruct budget availability control.
rgds
Saurabh
Hi Saurabh,
First,Thanks for your response.And I am totally agree with you.But,
Budget control actually happens through availability control prog based on which the ISBD status is set if there is insufficient budget.
I saw available budget around (no tolerance limit achieved)in S-..558 report and ISBD on WBS in PRD server.
I thought of running CJBN->CJEN and RKANBU01 in SA38.I encountered the same situation in DEV server and ran the above mentioned. But, what happens now : S-AL..558 gives me overall & actual budget figures as"0". Why this is happening?
Does running RKANBU01 does any harm?
Please suggest.
Regards
Ankur
HI Ankur,
I hope you have done the reconsturction in correct sequence. ie. RKANBU01, CJEN, CJBN in order.
RKANBU01 will iron out the PR,PO commitments. I dont think it can do any harm.
Have you done availability control analysis using CJ31 > Extras > Availability Control > Analysis > Type "=SUM" in command line and enter. (as i suggested in earlier post). Expand all the nodes and analyse the same. Can you share the screenshot?
rgds
Saurabh
Hi B P,
I found two similar cases in both clients.But my area of concern is PRD. So, before running above mentioned programs/jobs in PRD, I thought of checking in it DEV client first. And on doing the same I got above mentioned discrepancies.Yes, we have refreshed our DEV client recently and it is an exact replica of PRD . And,if you feel any other doubt please feel free to post here.
Regards
Ankur
Hi Ankur,
Putting the other issues aside,one thing is for sure that if CJ30/31 is showing budget value then the same should be seen in the S_ALR_87013558 report.The suggestion may be too simplistic, but can you please recheck if the values you are seeing in the report is for Total Budget or Overall Budget.Generally speaking to see the overall budget you need to scroll to the extreme of the report.
Running RKAUNBU01 should have no effect on the allocated budget(CJ30).So at least this value should be reflected independent of anything as per my knowledge.
Thanks and Regards
Hi B P & Saurabh,
I ran CJEN-> CJBN->RKANBU01 in the same sequence as it is mentioned here.Did I make it wrong?Saurabh, what analysis "CJ31 > Extras > Availability Control > Analysis > Type "=SUM"" can this process give when my concern is to see overall budget values in S-ALR..558 when there is value in CJ30,please suggest.I am attaching few screen shots which will give you exact picture of the issue.
As shown above we can see overall budget values in CJ30 but not in S_ALR..558. This is where I am stuck with after running CJEN-> CJBN->RKANBU01.
Please suggest.
Thanks & Regards
Ankur
Hi Ankur,
Did you check the settings of the report form in CJE5 (form 12KST1A). Check the characteristics for Budget/Actual columns. Hope that you might not have changed the standard settings.
Secondly try deactivating availability control using CJBW and then again reactivate it using CJBN (perhaps you might have tried this ealier)
Let us know the result.
Rgds
Saurabh
Hi Saurabh,
CJE5 settings are same as you showed in screen shot with value type 41,4,21,25 for column of budget,actual,commitment and remaining respectively.
I tried CJBW and then CJBN, but no gain.
In CJEN there is a check box"Delete" under processing options. Can this check box cause the error?
please suggest
Thanks & Regards
Ankur
Hi Saurabh,
I saw several columns in RPSCO mentioning about period value & annual value as shown below:
But I am not able to get what to know from it.Also business wise what values are stored in this table?If, I am right it stores commitment values against project/WBS, please correct if I am wrong.
Please help
Thanks & Regards
Ankur
Hi ankur,
Refer to column Value Type (WRTTP).
4 = actual
1 = Plan
21 = PR commitments
22 = PO commitments
41 = budget
45 = budget release
If you dont have any values with value type 4 then actuals wont appear in report. Ditto for 41 for budget display and so forth.
These are just some value types. You may take F4 help on that column to find out more.
The values in columns referes to individual periods and annual values in periods. Refer to RPSCO table structure in SE12.
Rgds
Saurabh
Hi Saurabh,
The concept " If you dont have any values with value type 4 then actuals wont appear in report. Ditto for 41 for budget display and so forth" is absolutely correct but it should be applicable for all the projects S_Alr..558 reports and I am getting values (budget,actual overall) for other projects which should not come as per our concept.
Also, I executed RPSCO without giving any value type.
Where is the problem then.. please help
Thanks & Regards
Ankur
As i mentioned earlier if there are no entries in RPSCO with Value Type =41 this simply means your report wont show the budget values. All cost reporting is done using RPSCO.
You need to reconstruct RPSCO which is done using CJEN. Now as you have already done that i understand you need to analyse the detail screen after running CJEN.
Try this
Step 1 :
Execute CJEN
Delete check box on
Detail list Check box on
Detail screen will show zero entries
Step 2:
Execute CJEN
Delete check box off
Detail list check box on
You will then get detail screen. Analyse this details for Value types i had mentioned in my earlier post.
If stil it doesnt work check if the budget entries are there in BPEG, BPVG, BPGE.
Hi Saurabh,
I found the entries in BPEG table but not in RPSCO.Also, I ran CJEN again with the selection criteria mentioned by you but now if I check S_ALR..558 I see "0" values again Budget, actual,remaining,commitment,assigned. previously I was able to see assigned,remaining & commitment values. But what was gone wrong now?
Also,What are the ideal processing option while running CJEN?
How can I populate data in RPSCO field?
Thanks & Regards
Ankur
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.