Precommitment after SRM SC

Former Member
0 Kudos

Hi Experts,

SRM 7 EHP 1

ECC 6 EHP 3

Classic Scenario

In ECC, currently Funds Management and Investment Management is active. In ECC, when a PR is created a Precommitment document is posted in FM. When PO is created a Commitment document is posted in ECC.

We are enabling SC in classic scenario and follow on document is PO (after SC approval) in ECC.

Please let me know -

1. Is it possible to post a precommitment document in FM once SC is created in standard SRM?

2. If yes, what are the touchpoints where configurations will need to be done to handle this?

Thanks & Regards,

Amish

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Amish,

The Commitment item can be posted only after approval of SC.  This is the std behavior of SRM.  If you want post a commitment after of ordering of SC,  you have to go for development.

Best Regards

Ram 

Former Member
0 Kudos

Hi Ram,

Thanks for your reply.

My question was related to precommitment document posting in Fund Management.

Is is possible in SRM Standard Classic scenario to create a precommitment document in FM upon creation/ordering/approval of SC?

FYI - SRM PPS supports Precommitment posting in FM upon SC ordering.

Thanks & Regards,

Amish

Former Member
0 Kudos

Hi Amish,

When you order the SC the Pre-commitment will only be posted after the approval be done (the sc is released). This is the standard. No other ways are supported without enhancement.

Thanks,

Melina

Former Member
0 Kudos

Hi Melina,

Thanks for your reply.

In a standard classic scenario (without PPS scenario) will a precommitment document be posted in FM (Funds Management module) after SC approval?

We do not have PPS scenario - hence is precommitment possible?

Thanks &  Regards,

Amish

Former Member
0 Kudos

Hi Amish,

Sorry. Without PPS this is not supported.

Thanks,

Melina