Contract CIF Error from ECC to SNC.

Former Member
0 Kudos

I couldn't interface(CIF) Contracts from ECC to SNC.Integration model for the Contract is being generated.Even after activation of Model is done, the Tlane couldn't be created.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ankit.,

Check below points:

1. First CIF Plant, material

2. Then CIF the contract

3. Check for any error messages in ECC

4. IN SNC check SMQ2 tcode , for queue blocks.

Hope this will solve your issue.

Thanks and Regards

Jagadev

Former Member
0 Kudos

Hello Jagadev,

We tried that. We checked contract's validity date, deletion flag, products, POs related to that. all is fine .. When we CIF single contract we are able to but together all. We cant .. Can you help out with that ??

Regards,

Ankit

Former Member
0 Kudos

Just check once if all plants/materials are there in SNC prior to CIFing

Regards

Vivek Jaju