on 05-22-2012 4:55 PM
Hi Friends,
I Have upgraded my SOLMAN 7.1 to SPS4 and finished the System preparation and Basic configuratio.Now when I am tring to new maintenance in MOPZ it is not openning and generationg runtime error
OBJECTS_OBJREF_NOT_ASSIGNED
Exception CX_SY_REF_IS_INITIAL
I also have check sapnote 1632595
But the mentioned entries are already there.
Kindly share your inputs to esolve the issue.
FYI: It was working fine before Patchupgrade.
Regards,
Satyabrat
Adding to it Please find the dump details as beow;;;
Category ABAP Programming Error
Runtime Errors OBJECTS_OBJREF_NOT_ASSIGNED
Except. CX_SY_REF_IS_INITIAL
ABAP Program CL_MO_CRM_ADAPTER=============CP
Application Component SV-SMG-MAI
Date and Time 22.05.2012 20:45:32
Short text
Access via 'NULL' object reference not possible.
What happened?
Error in the ABAP Application Program
The current ABAP program "CL_MO_CRM_ADAPTER=============CP" had to be
terminated because it has
come across a statement that unfortunately cannot be executed.
---------------------------------------------------------------------------------------------------------------------------
If you have access to SAP Notes, carry out a search with the following
keywords:
"OBJECTS_OBJREF_NOT_ASSIGNED" "CX_SY_REF_IS_INITIAL"
"CL_MO_CRM_ADAPTER=============CP" or "CL_MO_CRM_ADAPTER=============CM00C"
"GET_CRM_ID"
----------------------------------------------------
Regards,
Satyabrat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you please check in Landscape verfication tool (tcode LVSM) if the products and product systems are correctly maintained for the system . Make sure the LVSM has updated data from SMSY.
You can update in LVSM and remove the errors if any for that system.
Once done , update the change in SMSY. ( There is an option available)
Then you will be able run MOPZ maintenance transaction without issues.
Regards
Ratnajit
Hi All,
This issue is not resolved yet. We also raised this to SAP with HIGH priority but not getting expected response from them. According to them the issue is forwarded to MOPZ development team.
@Josh - Kernel is in latest release
@Ratnajit - I have checked LVSM there is many wrong entries..But I dont think this may the reason as at least mopz should work with the system those are correctly maintained. It is throwing error immediately when starting a new transaction..
Kindly share your valuable inputs to get rid of this issue.
Regards,
Satyabrat
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.