Hi Expert,
I need your help regarding a safety stock scenario to be integrated in PPDS; currently in Safety Stock in SNP is customize having a table with the list of safety days that to be apply during the SNP heuristics. Since we are not able to apply the standard configuration, is there any BADI's that we can use to adopt safety days in the production planning run. We are using 'MZ' safety stock method, so Im not sure if I can use the BADI - /SAPAPO/RRP_SFTY_STK.
Is there any BADI available that I can use just to customize our requriements and incorporate our custom table in the PP run.
Thanks
Regards,
Lon
Hi Lon,
To work with time-dependent safety stock methods (MB, MM, or MZ) or a scenario other than make-to-stock production, you use the BAdI /SAPAPO/RRP_SFTY_STK (method UPDATE_IO_NODES).
Thanks,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.