on 05-19-2012 12:12 PM
Dear Team/expert
We have scheduled SAP_REORG_ORPHANED_JOBLOGS as background job on weekly basis in production client. But it delete 1 job once in a while that is only from 000 client..Below is details of variant
1000 Display Only P
1000 Display and Check P
1000 Delete P X
1000 Maximum Size of the Selection P 20,000
i checked SAP NOTE# 666290.it's suggesting there should be one more option 'Continue in spite of warning' in variant. But you see no option like that.
I think we require to update the program as per attachment in SAP NOTE# 666290.
Please suggest,,,,,
The note you mentioned may be applicable for your release. Also your system seldom have orphaned jobs , thats the why the job only deletes orphaned jobs once in while.
Do you see a lot of old joblogs in the fileystem ?
Regards
Ratnajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ratnajit,
OK.. I agree, we haven't much orphaned jobs
But Note says, there should be one more option" Continue in spite of warning' in variant.
and also attached 1 zip file with this note
please check...
Presently, we have
SAP ECC6.0(EHP4), Kernel release-> 701;
SAP_BASIS: Release-> 701; Level-> 0007
Database: Oracle (10.2.0.2)
The code correction is not applicable for your scenario as the report RSTS0024 already should exist. The attachment contains text elements which the code uses and is ABAP related.
You check the report which runs for the job SAP_REORG_ORPHANED_JOBLOGS and these are the variants available . The option selected in the variant is fine . You can increase the maximum size of selection to 30000, but make sure enough memory is available .
Regards
Ratnajit
User | Count |
---|---|
80 | |
24 | |
11 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.