Hi users,

I am new in SAP Plant Maintenance Module.

In my company we want to link a Equipment to anther Equipment through SAP .

Please give me the information regarding this.

Example is as with a Batching Plant(Log No. is B01001001) two D.G. Sets(Log No's are P43004001 & P43004002) and a Air Compressor(E0001001) is attached.

Can we create Equipment BOM?

or any other process is available in SAP PM module.

Please suggest me.

also give me the process regarding this.

Thanks & Regards

Vikas Gupta

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

you can attached the subordinate equipment to superior equipment. first create the superior equipment as Batching plant, and while creating other equipments specify the superior equipment as Batching plant and save

regards

thyagarajan

Former Member
0 Kudos

Dear thyagarajan,

Thanks for reply.

Please suggest the T codes and process to create this.

Thanks..

former_member187991
Active Contributor
0 Kudos

hi

it is just creation of equipment IE01 only

regards

thyagarajan

Former Member
0 Kudos

Dear Thyagarajan,

thanks for reply and support.

can you give me some study material related to SAP PM module Plz.

Thanks & Regards

Vikas Gupta

former_member187991
Active Contributor
0 Kudos

hi

kindly practice in IDES with the help of following link

http://help.sap.com/saphelp_46c/helpdata/en/fe/67f9609d6f11d189b60000e829fbbd/frameset.htm

and explore the SAP help

regards

thyagarajan

Former Member
0 Kudos

Dear Sir,

Please mail me some documents as format pdf or docs.

I will grateful to you.

Thanks & Regards

Vikas Gupta

former_member187991
Active Contributor
0 Kudos

From my understanding those links were more useful than documents

regards

thyagarajan

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Vikas, Tyhagarajan,

You can create an Equipment category at any time

Just go into your Batching Plant in IE02, select Menu > Structure > Sub-equipment (Shift+F11) and specify the numbers of your sub-equipments.

This is similar to structuring FLocs or Equipment installation in FLocs.

Answers (0)