Available capacity for workcenter .

former_member232086
Participant
0 Kudos

Experts,

In the below case the available capacity of the this machine (RK33) is showing only 396 Hrs but for all other work centers it is 744 hours. May i know why is it happening?

Regards,

Vijesh.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vijesh,

You don't supply much information.  The real question should be "what is the capacity for WRK33"?

It's derived from the Time-Continuous Capacity and SNP Bucket Capacity in the Resource master.

The number of hours in SNP should match the hours in PP/DS.

Best regards,

Mike

former_member232086
Participant
0 Kudos

Hi,

it was 50 % but we changed it 100 % still not working.

Regards,

Former Member
0 Kudos

Hi Vijesh,

I think what you are saying is that the master data for RK33 is not updated in SNP after the change to the resource master.  Try running transaction /SAPAPO/TSCONS to update the master data.

Best regards,

Mike

Former Member
0 Kudos

Vitest,

Also run /SAPAPO/OM17 for resources.  Then /SAPAPO/TSCONS.

Mike

Former Member
0 Kudos

Sorry, I meant Vijesh.