SNP Opti - Planning on Sales Order Req. Date in Past

former_member566355
Participant
0 Kudos

Hi,

in SNP optmizer, Is it possible to take sales orders into planning whose requested date is in past?

If not, how such sales orders should be handled from planning point of view? We want the sales order to take part into planning.

Regards,

RS

Accepted Solutions (0)

Answers (1)

Answers (1)

rajkj
Active Contributor
0 Kudos

Hi RS,

If you need to consider past due orders or backlogs, your planning horizon (data view's time bucket profiles must include one for past).

Please check the following note for details.

https://service.sap.com/sap/support/notes/481707

Thanks,
Rajesh