on 05-14-2012 10:48 AM
Hello SAP Gurus,
We are working on SRM 7 extended classic scenario.
I have created the limit order po for 100 CHF and tax as 0.Once it got approved i try to create confirmation for 101 CHF but it is giving backend error "service & : no overall limit for unplanned services amounting to & exists".But we are maintaing tolerance in srm system LA 5%.Hence it is not giving error message in SRM.Is there any way to make tolerence check for confirmation in backend system.
Advance thanks for clarification.
Regards,
Shiva
Hi,
While creating the service PO, one should maintain the overall limit in the 'Limits Tab' of PO. This is generally maintained for unplanned services.
Now maintain PO value as well overall limit value which can be greater than PO value. Then create confirmation again; now the confirmation value can be greater than the PO value but it has to be within the overall limit value.
Check if it solves your issue and do the document gets posted in backend as service entry sheet?