on 05-12-2012 9:26 AM
Hi,
We are using standard planning book for managing storage capacity. The product master has GI time of 10 days and we expected the storage capacity consumption at sending location at the end of GI date, but what we see is the storage resourcecapacity consumption at the start of GI.
Is this behavior SAP APO standard and is there a way to manipulate the capacity consumption at the end of GI date/time.
Thanks.
Sandeep
Hi,
SNP heuristics use GI/GR process times for scheduling while generating the proposals.
Then, storage capacity consumption is a calculated quantity (based on the macro 'Stock Balance'). For a given time period (bucket),
Projected stock = Projected stock of previous time period + Total Receipts - Total Demands
The stock derived based on the above formula drives the storage resource capacity requirements.
GI process time or Storage capacity requirements are not directly influence each other. The SNP planning engine use them in the process flow.
I hope this explanation does not confuse you further .
Thanks,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.