PI ccBPM corelation : deadline reached

Former Member
0 Kudos

Dear Experts,

We are working in PI 7.11 , we have a ccBPM scenario in which we have the corelation used.

The scenario is BPM receives the delivery IDOC from ECC and waits for the corresponding Invoice IDOC to receive. The key is delivery number.

Once both the IDOCs are received, a multi-mapping is used to generate new message and send to Customer.

The problme is when the delivery IDOC is received it starts thse new process and wait for the Invoice IDOC to come, but if the Invoice IDOC is not reached in 3 days then the BPM is saying "deadline reached" and the process will be rolled backed.

Please suggest, how we can increase the deadline and process waits for longer period.

thanks and regards,

Ravi Siddam

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

is this what you mean?

- select your deadline branch in your integration process

- and set the duration in the properties

this is a screenshot of the SAP example "BpmPatternCollectTime"

iaki_vila
Active Contributor
0 Kudos

Hi Ravi,

If you want to increase the deadline period you can follow the Santhosh Kumar sugerency: http://wiki.sdn.sap.com/wiki/display/XI/BPM+Trouble+Shooting+Deadline+Step

Regards.