OpenPS WBS Actual Dates

fortian
Active Contributor
0 Kudos

Dear Experts,

We are doing some tests with OpenPS in order to download our projects to Microsoft Project.

We are only using WBS (no networks).

I've read "While costs and actual data can be downloaded to MS Project from SAP PS, these cannot be uploaded back to SAP PS.” but I haven't succeed downloading the actual dates of the WBS.

Any idea of what we might be missing?

Thanks,

Fortian

Accepted Solutions (0)

Answers (1)

Answers (1)

fortian
Active Contributor
0 Kudos

We have already mark the option "Download Actuals" (When downloading project".

Could someone confirm that network actual dates are the only ones that can be downloaded? And not the WBS actual dates?

Thanks

fortian
Active Contributor
0 Kudos

We have been testing with cost activities and we can't get to download the actual dates of the activities to Microsoft Project, any idea?

Could someone give us some advice?

Thanks in advanced.

fortian
Active Contributor
0 Kudos

Please bear in mind that in SAP PS, after confirmation, actual dates do not affect the planned dates while in MS Project, actual dates might change the planned dates.

For e.g. if actual start date is before planned start date, MS Project will push back the planned start date to match the actual start date.If actual information has been recorded in SAP PS, check the baseline information in MS Project to see the planned information.