CJ34: Receiver WBS not received the transferred amount

Former Member
0 Kudos

Hi Experts

I have used CJ34 for transferrring budject from project A to Project B.

The sending amount updated in Project A but not updated in Project B as received amount.

1) What would be the reason?

2) How to correct this?

thanks

ramSiva

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Hi Siva,

1) Check in cj3a /s_alr_87013560 /cji8 for budget updates.

     Validate the transferred amount in year/overall.

Regards

Former Member
0 Kudos

Hi

Check any releasing process is active.

Regards

Rao

former_member221039
Active Participant
0 Kudos

before doing cj34, check cj33, the release amount, and released amount be reduced as required to transfer amount so that you can carry out cj34.