on 05-08-2012 7:04 AM
Hi,
We have a 2 activities in the Project, my requirement is successor activity should not be released untill predecessor activity status Release.
I have checked the all possible options still it is not working, Pl. share your inputs.
Venu
Hi All,
I got the solution. We can achieve it by the following User Exit
"CNEX0028:Check activity release"
My issue is solved now, I'm Closing the thread.
Thanks.
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you checked the milestone functions option? Check that once and revert.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pillai,
Thank you for response.
We knew that we can control network activity flow through Milestones -like Milestone release and stop indicator functionality.
But my client requirement is, can we control the releas of actiivities through activity statuses.
Like, I have 100 activities in the project, client is not interested to go with milestone assignment for each activity and to control the process flow of activities.
Here If the first activity is with status "CRTD" then system should not allow me to Release its succeeding ativity ie., 2nd activity.
Pl. share your inputs on this.
venu