Partial settlement not required Extended Rebates

noumanahmed_khan
Participant
0 Kudos

Dear All,

I have configured Extended rebate agreement for monthly partial settlement. Assigned Settlement calendar and payment procedure 'A' still i am getting below information

"Partial settlement not required (agreement: 38 - period: 01.03.2012 to

31.03.2012)"

On Issue SIS Vol  i am getting information

"There are no sales to be settled for agreement 38

    Message no. BON_ENH_MESS108"

However I have posted invoice for the month of March.

Thank you,

Regards,

NoMi

Accepted Solutions (1)

Accepted Solutions (1)

noumanahmed_khan
Participant
0 Kudos

Dear All,

I have found the solution for the error on document "Extended rebate (G63) building block configuration guide" Last Paragraph on website

http://help.sap.com/bestpractices/BBLibrary/html/G63_ExtRebate_EN_DE.htm

A relevant update routine needs to be inserted for extended rebate which updates Table S469.

This configuration step is necessary because of a missing entry in table TMC2F (refer to OSS Note 734828). This table should consists of relevant Update Routines for rebate related Info Structures. Since this table has no maintenance dialog, the missing entries have to be transferred via an written ABAP program or via BC Set /SMB26/TMC2F_B002_G63 (refer to installation guide for G63).

Thank you,

Regards,

NoMi

Lakshmipathi
Active Contributor
0 Kudos

Nice to see that you had the courtesy to update how your issue was resolved.  Continue this good work.

G. Lakshmipathi

noumanahmed_khan
Participant
0 Kudos

Thank you G.Lakshmipathi

Answers (0)