on 05-07-2012 12:24 PM
Hello experts,
Could any one please help me in telling the prcess of moving documents from solution manager dev system to solution manager quality system ( export/import).
Regards,
Praveen
Hi
This is very simple
just goto solar_project_admin
and from SAP Menu choose the option PROJECT->TRANSPORT
( this option will import project with strucutre in solar01 )
then store it in a request and move the project request to your quality system via STMS etc.
Hope it helps
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
project can be transported ir respectiv of its status and the status of documents,
Please refer this http://help.sap.com/saphelp_em70/helpdata/en/ee/cfe93a2876a81ae10000000a11402f/content.htm
Thanks,
Jansi
HI Praveen,
For transporting the project including document , check the below link
http://help.sap.com/saphelp_sm32/helpdata/en/ee/cfe93a2876a81ae10000000a11402f/content.htm
Rg,
Karthik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.