Dear SAP,

     What are the setting required in define key  certification processing for the scenario:-certification is receive before good receipt.

Best regards,

Asif

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member184536
Active Contributor
0 Kudos

Hi Asif

go through the displayed link.

http://help.sap.com/printdocu/core/print46c/en/data/pdf/QMPROC/QMPROC.pdf

In Customizing for QM in Procurement, the following conditions must be met:

  A QM control key with indicator Certificate required is set

  A certificate type has been defined and the indicator for enhanced certificate processing is

set

  A number range for the certificate receipt is defined

In the material master, the following conditions must be met:

  QM in procurement is active

  A control key with certificate requirement is set

  A certificate type is specified

Features

This function covers the following scenarios for processing a certificate:

  Certificate is received before the goods receipt

The receipt of the certificate is recorded with reference to the purchase order. You

choose the transaction to record a certificate receipt, and enter the purchase order

number, the purchase order item and, if known, the delivery number.

With regards

Manish

former_member216607
Participant
0 Kudos

Hello Manish,

   I have maintain the control key & Certificate type,But while GR it not allowed me to accept GR.I maintain certificate  by QC51.But then also it not allowing me to do GR.

Regards,

Asif

former_member184536
Active Contributor
0 Kudos

Hi Asif

What msg it shows while doing the GR?

Manish