on 05-07-2012 6:41 AM
Hi Experts, I have procured a material by attaching material to a network activity. Now it is in project stock. I want to track the consumption. Is there any process to issue material and track consumption. Please help me..
Thanks & Regards,
Dileep
Hi,
Please check CN52N report.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What do you exactly mean by tracking material consumption? Have you referred the report MBBS and checked if it satisfies your requirement?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.