Hi Experts,  I have procured a material by attaching material to a network activity. Now it is in project stock. I want to track the consumption. Is there any process to issue material and track consumption. Please help me..

Thanks & Regards,

Dileep

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Please check CN52N report.

Regards

Shrikant

Former Member
0 Kudos

What do you exactly mean by tracking material consumption? Have you referred the report MBBS and checked if it satisfies your requirement?

Former Member
0 Kudos

Hi Gokul,

Thanks for the reply.

In MBBS, i can see the stock, but i want to know how much had been consumed. Is there any process to consume material so that we can check the report for, what is the stock available and how much had been consumed?

Thanks,

Dileep

Former Member
0 Kudos

Hi,

Try using MB52 at Plant level or individual component level which will let you know the status of material at warehouse level.

In CN52N, you can see the withdrawal quantity agains requirement and received quantities.