05-06-2012 6:13 PM
Hi
I have successfully created rules to ensure that you can't transfer or return budget to less than 0. But I also need to ensure that the original budget is not reduced to less than what has been released either by transfer or return. How can I do that as I'm struggling with that?
Thanks
05-07-2012 8:29 AM
Hi,
Please make sure that this note is implemented in your system:
1616258 Release: no error if we decrease budget amount in a doc
kind regards
Mar
05-07-2012 8:29 AM
Hi,
Please make sure that this note is implemented in your system:
1616258 Release: no error if we decrease budget amount in a doc
kind regards
Mar