Project or project branch does not contain any planning elements
Message no. KPN082
Diagnosis
The project or project branch to be processed does not contain any planning elements.
System Response
The system cannot create the costing.
Procedure
Select the WBS elements you want to cost as planning elements.
Note that costing is not possible for plan-integrated WBS elements, even though they are planning elements.
The purpose of integrated planning indicator is integration with controlling cost centre accounting etc- this can be unticked and it does not mean statistical unless you select statistical - then it would be statistical and useless for quotation