Hi Experts,
When i am attaching material to network activity, i am not getting pr creation option to select. It is directly creating reservation without asking any option.
I have maintained the Pur\res option ( For release) in network profile.
Please let me know what could be the problem?
Thanks & Regards,
Dileep
When you attach the material to an activity what is the item category that you choose? Is it N or L? If you want system to create a PR for tha attached material please use the item category N. You can also check the MRP tabs in the material master to check whether individual or collective requirement is maintained there.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In case you want PR directly, assign the material as non stock 'N' and not as stock 'L'
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check whether it is collective requirement or individual requirement in the material master MRP tabs
krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.