Hi,
is it possible to create a hammock task within cPro/ PPM 5.0?
A hammock task e.g. is connected with one milestone before the task and one milestone after the task has been completed. If I postpone the milestone after the task, I would like that the system automatically extends the duration of the task (without craeation of a between the task and the second milestone).
Thanks,
Hi,
Hammock was used in P3.
In Primavera6 (or latest), I would assume, 'Level of Effort' activity is used in place of Hammock. For which standard relationship/scheduling logic might work with/without enhancement.
If you are referring 'Milestone' activity of P6, pl try using task with 'milestone' flag. Try using finish-finish relationship. BAdI enhancment will help as well!
thanks
Mathavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Unfortunately, this feature is not available in the current PPM solution, neither in 4.5 nor in 5.0 release
BR
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
6 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.