on 05-04-2012 7:20 AM
Hello
When I do KKA2 for the customer project, the system give the following message:
Planned costs for valuation are 0. Please check the object
Message no. KJ216
But actually I have planned costs , actual costs, for that period , I can see them in the project report.
Could you please let me know why the system is throwing an error while running KKA2?
Thanks for your help,
Vadiraj K
Hi,
This is the note that will probably help you resolve your issue,
Note 1159784 - Results analysis: no planned costs for valuation
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check SAP Note 388354
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.