Subcontracting Preq within Stock Transfer Horizon

Former Member
0 Kudos

Hi Experts,

We are encountering an issue when running SNP Heuristics. This is for Intercompany scenario, where Purchase Requisitions are created inside the stock transfer horizon.

I have set in Location A: 7 days of stock transfer horizon.

Thanks a lot in advance for you help!

Regards,
Kris

Accepted Solutions (0)

Answers (1)

Answers (1)

rajkj
Active Contributor
0 Kudos

Hi Kris,

Reproduced from the thread http://scn.sap.com/thread/3167507

The following notes might be helpful. Please check.

https://service.sap.com/sap/support/notes/1045636

https://service.sap.com/sap/support/notes/1521556

https://service.sap.com/sap/support/notes/1231360

https://service.sap.com/sap/support/notes/1601536  - considers the time zone effects

https://service.sap.com/sap/support/notes/1649238

 

https://service.sap.com/sap/support/notes/1638031 - Source of Supply validity period (may not be applicable for your issue).

Thanks,

Rajeshh