Dear Expert Plz. confirm in CN60 Report history provide only network level ,WBS and Project Defination Change history not Provide. plz. confirm the problem . Even Change Document tick also available in PD/WBS/network Level.

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

hi mayoor

GO TO the t-code OPSA. there you will find the change document check box. press f1 there and then read the help document it is clearly written there that change document will only work if the project is released (REL). so released the project


Former Member
0 Kudos

Hello Mayoor,

Please check in the Menu Project System -> Information System -> Structures -> Change

Documents -> For Project/Network

Change documents are written for the master tables like PRHI, PRPS, MLST etc.,  The change documents are written whenever there is a change in the basic WBS element data.

Regards, Gordon

Makal
Active Contributor
0 Kudos

What is the system status? Change document works only after "REL" status is set.