WM-PP Material Staging .

Former Member
0 Kudos

Dear All ,

My requirement is to stage materials from different storage locations which are part of a single production order to production bin, with help of supply area and control cycle.

Work center for these materials is the same.

how do i achieve staging on above scenario.

Thanks in advance

Jinoy

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear all issue is resolved , thanks for your kind cooperation.

Former Member
0 Kudos

Hello Jinoy,

How did you solve this issue?

Regards,

Charu

Former Member
0 Kudos

Hi Charu  , We are currently staging  from single storage location .

Former Member
0 Kudos

Hello,

One work center has one PSA and one PSA can be attach to one sloc only. In your case as you are having same WC for all sloc, you can not achieve this for single WC.

BR

Former Member
0 Kudos

By Using KANBAN cards and barcodes