cancel
Showing results for 
Search instead for 
Did you mean: 

BADI - Converting Purchase Requisition to Purchase Order

Former Member
0 Kudos

hello All.

I need change some information before convert P. Requisition to P. Order.


Anyone knows if have a point where i can do this?

Thanks and Best Regards

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello DEv and Rajesh.


Thanks your answers.

These BADI are in ECC Side?

Do you kno on SCM side??

Thanks and best Regards.

rajkj
Active Contributor
0 Kudos

Hi Marcelo,

The user exit that I mentioned is available only in SCM i.e. APO. The BAdI that Dev mentioned are available in ECC.

Thanks,

Rajesh

dev_shetty
Active Participant
0 Kudos

Hi Marcelo,

                    For your requirement best place to define enhancement is ECC not APO. I am not sure why you are looking for BADI in APO. The std process in APO generates Preqs and they are transferred to ECC and converted to POs.

Thanks

Dev

rajkj
Active Contributor
0 Kudos

Hi Marcelo,

You can use enhancement APOCFPEP to change external procurement documents, for example, purchase orders and purchase requisitions before they are published to SAP R/3.

Thanks,
Rajesh

dev_shetty
Active Participant
0 Kudos

Hi Marcelo,           Please explore following 2 BADI's. One of them should meet your requirement. -ME_REQ_POSTED- BAdI: Define Follow-On Processing for Purchase Requisitions -ME_PURCHDOC_POSTED-BAdI: Define Follow-On Processing for External Purchasing Do Thnaks Dev