SAP for Utilities Discussions
Connect with fellow SAP users to share best practices, troubleshoot challenges, and collaborate on building a sustainable energy future. Join the discussion.
cancel
Showing results for 
Search instead for 
Did you mean: 

Valuating the Success of Dunning

Former Member
0 Kudos

​Hi,

Does someone have used "Valuating the Success of Dunning" ?

It is an option in collection steps : checkbox "perform success valuation"

Is there performance issue with the batch which calculate the % of success ?

Could you give me a feedback of this functionality ?

Thanks

Mathieu

3 REPLIES 3

william_eastman
Advisor
Advisor
0 Kudos

Mathieu:

I have worked with a few customer that have implemented the valuation process.  They experienced no performance problems.  They only ran the valuation on a weekly basis outside the nightly process.

regards,

bill.

0 Kudos

Hi William,

Thanks for your answer.

I have 2 more questions about this topic :

- in your previous implementation, do you have changed the logic in the exit FKK_SAMPLE_0393 ? Or do you used the standard code ?

- Is the dunning program run slowly after implement "Valuating the Success of Dunning ?

In our system we have 7 000 000 contracts accounts, so performance issue is very important...

Thanks,

Mathieu

0 Kudos

Mathieu:

No, we did not enhance the event.

No, there was no impact to the dunning process - why do you think there might be?

regards,

bill.