My client requirement is as follows once Production is confirmed(final confirmation) the material will move to Reservation,they need

a check point or after stores approval it should move to reservation.please help me on this scenario.Is there any option

regards

vasanth

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

Please check the following:

Depending on the settings in the material master and the bill of material, or the settings and assignments in the project system, the system generates for components with this item category a reservation once it is reservation type it is moved

Please look into the following:

http://help.sap.com/saphelp_46c/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm

regards

Former Member
0 Kudos

Thanks swetha helpful  answer for me. i can assign 10 points to you.