on 04-25-2012 2:35 PM
Dear all,
My client requirement is as follows once Production is confirmed(final confirmation) the material will move to Reservation,they need
a check point or after stores approval it should move to reservation.please help me on this scenario.Is there any option
regards
vasanth
Hello,
Please check the following:
Depending on the settings in the material master and the bill of material, or the settings and assignments in the project system, the system generates for components with this item category a reservation once it is reservation type it is moved
Please look into the following:
http://help.sap.com/saphelp_46c/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.