Batch should not change in Sales process.

Former Member
0 Kudos

Hi,

If we addedd batches in sales contract(Va41). it should not be change any further process.

Can any one suggest the config/development.

Regards

Gajanan Rudrakanthwar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

If the same material exists in multiple batches based on the sort rule it will come and in the delivery level(standard) have access to change the batches. If you want to restrict only option is you have to grey out (disable) the batch split field.

The requirement you are asking is not possible in the standard.

DVNR.

Former Member
0 Kudos

HI,

If i am using Contract to sales order and willing not change batches in sales order how i can gray out the sales order field.

Regards,

Gajanan

Former Member
0 Kudos

As i suggested earlier it is not possible in standard if you have multiple batches if you have one batch it will come in display mode,even though if you change manually system gives error as batch number wrong (Just like plant..if only 1 plant is assigned to ur co.code case).

Or else you can try with MV45AFZZ contact your abaper regarding this and explain the issue.

DVNR.

Former Member
0 Kudos

thanx will check it

Former Member
0 Kudos

Hi,

If you feel my answer is helpful mark as helpful.

DVNR.