Budget commitment with material reservation

Former Member
0 Kudos

Hi,

Is there a way that a material reservation make a commitment against my budget/grant? I'm using PS and FM and I'd like to know if is possible to make some configuration to achieve this.

Thanks in advance,

Icuk Hertanto

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

If you do the budgeting in PS and using network activity, the reservation made for NWA will be considered as Remaining Order Plan which will book the budget

Former Member
0 Kudos

Amaresh is right. There will be no CO commitment from material reservations. Please also see SAP note 91036  for explanation.

There is no chance to have commitment update.

Regards, Gordon

Makal
Active Contributor
0 Kudos

Is there a way that a material reservation make a commitment against my budget/grant?

I do not think, in standard system it is possible. You may need to do development.