on 04-20-2012 7:39 AM
Hi,
Is there a way that a material reservation make a commitment against my budget/grant? I'm using PS and FM and I'd like to know if is possible to make some configuration to achieve this.
Thanks in advance,
Icuk Hertanto
If you do the budgeting in PS and using network activity, the reservation made for NWA will be considered as Remaining Order Plan which will book the budget
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amaresh is right. There will be no CO commitment from material reservations. Please also see SAP note 91036 for explanation.
There is no chance to have commitment update.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is there a way that a material reservation make a commitment against my budget/grant?
I do not think, in standard system it is possible. You may need to do development.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.