on 04-20-2012 7:50 AM
Hi,
I am having one Project in which few material components have been assigned to Network with procurement type "PReq + Reservation for WBS Element".
For these materials, GR has been done against specific PO.
Now our user wants to know whether can he reverse GR of these items, take out storage location and leave it blank.
So that user will not have an issue to do Goods issue.
Is this possible?
Regards
Tushar
Hi Tushar,
What is the problem in doing GI after GR?
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You should be able to reverse it.
Please refer following SAP help links, it's explained clearly.
http://help.sap.com/saphelp_46c/helpdata/en/0c/57ce370b39b73ae10000009b38f8cf/content.htm
http://help.sap.com/saphelp_470/helpdata/en/3a/78cd3719268514e10000009b38f842/content.htm
Thanks,
Amaresh Makal