on 04-19-2012 10:13 AM
Hi Gurus,
I need to have a check before MRP Run for Budget Release. Is there any standard setting available, or should it be through user status only. Pl confirm.
If its through user status settings, please guide through the process.
Thanks.
AM
Hi Murthy,
User status you can use to ensure that no commitment is created on the project until project is budgeted. Availability control, you can decide, whether you want to activate immediately after budgeting or budget release.
Thanks,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can refer following threads for setting up user status to check commitment creation on project before project release:
http://scn.sap.com/thread/1561630
http://scn.sap.com/thread/1623241
http://scn.sap.com/thread/959013
Regards,
Amaresh Makal
Murthy,
You can set it up in OK02. Set up user status - ZBUDG. Assign this status profile to project profile.
In object types, you can chose WBS element, Network header, Network activity.
You can have two statuses: Init (Initial), BUDR (Budget Release)
In in Init: Forbid all business transaction except Budget release.
In BUDR: Allow the business transactions you want to allow
I hope this helps you.
Regards,
Amaresh Makal
Thanks for support.
I have created user status as mentioned above and assigned this user status profile to Proj Defn and WBS in project profile, so that Project release is not possible in CJ20N.
All works fine till budgt release.
The problem is now I am not able to release the project in builder. The status is not changing to BUDR. After Manual change of status also, the same is the case, but i have allowed all transactions for BUDR status. The error message is "User status INIT is active". Help to sort this out.
Thanks.
AM
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |