on 04-17-2012 11:18 PM
In the Selection Profile, you have the option of setting an absolute or relative horizon (Time Related Selection Attributes). As far as I can tell, absolute prevents any rounding, but relative allows rounding to a date.
Is there any other impact by using absolute beyond that?
Thanks, Mike
Hi Mike,
Demand Horizon is used to select transportation requirements for planning based on dates.
Absolute:
The dates are fixed. For example, you want to plan for transportation requirements between May 01, 2012 to May 15, 2012. You specify Start Date = 05-01-2012 and End Date = 05-15-2012.
This little cumbersome in production environments as we have to change/check the dates before every planning run. I guess customer use this setting very rarely.
Relative:
As the name suggests, the selection is relative to the current date. For example, you always plan on every Monday for next three weeks. You will do the following settings:
Offset = 7 days
Duration = 21 days
So,
Start date for planning = Current date + 7 days
End date for planning = Current date + 7 days + 21 days
This is more likely to be used, because the dates roll by themselves. So, on 04 -23-2012,
Start Date = 04-30-2012
End Date = 05-20-2012
Again on 04-30-2012, you need not change the settings and new start and end date will be
Start Date = 05-07-2012
End Date = 05-27-2012
Hope this helps.
Regards,
Nagesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.