Hi All,

I am Using ROEMPROACT in ECC to transfer the demand and stock.

But it is failing in SNC.

getting the below errors:

Detailed Information

Start of inbound processing: ProductActivityNotification (ID 0000000000018673) 000(/SCA/BIF_PROACT)

TST 20120416234655 (type MessageCreationDateTime) was transferred as local time, interpretation as UTC 022(/SCA/BIF_MI)

Partner(s) is(are) not found 011(/SCA/DM_MDL)

Party 1010 is not maintained 085(/SCA/BIF_MI)

SenderParty is invalid 037(/SCA/BIF_MI)

Can somebody help me to resolve this issue.

regards

shailesh    

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I have tried using ROEMPROACT2 report also but still getting the same error in SNC .

Can anybody let me know if they have gone thru the same prob.

shailesh

Former Member
0 Kudos

Hi Sailesh

Did you get this issue fixed? I have same error, pl let me know

Thanks

Vipin

Former Member
0 Kudos

Please review the selection criteria once in ROEMPROACT2 and if all the master data is available in SNC and active model and BP assignment done correctly.