Recently I have uploded lots of projects through BAPI upload program. once the projects get successfully uploaded it's by defult comming into REL status.
We are also closing the project through LSMW. Now business wants to view status change dates of project through CJ20N transaction code.
My question is, is it possible to view status change dates in CJ20N and why the dates are not populating?
I am looking forward for your reply.
Regards,
Amlan
Hi Amlan,
In order to view status change dates, you need to tick 'Change Documents' in 'Status Management' section of project profile. This will work for WBS status change documents for new projects created after this change. Similar config is available in parameters for network type if you want to see network change documents.
After making these changes, you can see status changes in CJ20N itself. Click the i button after status and follow Extras>Change Documents.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Follow suggestions as furninsed by our friends and after that, you can also have it using program, go to transaction SA38, and enter RBSVCDOC in the field "Program". Select the Execute button. Insert your WBS/Network object number, and select the tick box "SHOW_ALL" Execute the program.
It will show you all the status against the object.
Regards,
Sudhakar
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.