on 04-16-2012 6:36 AM
Hi Experts
In my project, For completion of one internal activity it requires certain manpower hours and labour hours.
The cost is driven through Activity Type, which i assign it in my work centre-which further assigned it in the Activity. I can only assign one activity type in my Network Activity, which could be either for manpower or machine.
How do i calculate both the variable together for completion of one activity.
Is PRT a solution, as i haven't worked on the same.
Your Vital inputs required
Thanks and Regards
Simon
Hi,
The available best option would be using "activity elements" and assign difference work centre so that it will take care of your requirements.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Simon,
Please explore the option of activity element. You can break activity into elements and assign different activity types to elements. Hope this helps.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Explore the option of PRT's. You might get some more benefits by using PRT's to fulfill this requirement. Else you can also think of using activity elements for this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Simon,
why don't you use activity elements under that activity? This way you can capture both the cost under that activity.
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.