Dears,

Can anyone explain me that what is maintenance plan simulation in ip19?

i am getting only one plan while selecting the maintenance plan simulation in ip19?

Why it is showing like that?

when i select maintenance item overview it shows all the plans?

please explain what is maintenance plan simulation?

Regards,

Varma.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Simulation can be done only for the Scheduled Hold orders. You can't do for any other orders with order order status.

You can do the following.

1. You can fix the date of particular call object

2. You can fix the dates of subsequent call objects by setting one call object date. Eg: By setting first call object date (either advancing or postponing), you can reflect the same changes in subsequent call objects.

In IP10, you fix up the call for single call object. In IP19, you can do it for single or multiple call objects.