Hi

i have one query , when we create a consignment issue order for a material with 2 quantity and creates a delivery for only one quantity, in this scenario when I check the consignment issue order, its Processing status at item level shows completed as over all status and fully delivered as delivery status. (as shown in the image below). But actually we had done delivery of only single quantity out of two. can you explain why this happens.

Thanks

Madhur

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Check your item category completion rule where it should not be "A".

G. Lakshmipathi

Former Member
0 Kudos

Hi

Item category completion rule is blank , is this the reason that it is taking the status as complete ?

Lakshmipathi
Active Contributor
0 Kudos

In the copy control VTLA, what routines you have assigned ?  It should have been

a)  101  for both Order requirements and Item data

b)   Positive sign for the field Pos./neg. quantity

G. Lakshmipathi

Former Member
0 Kudos

HI Lakshmipathi

it is maintained is the same way you have recommended.

what else should i check or configure to get the desired response ?

or this behavior is standard one ?

Thanks

Shiva_Ram
Active Contributor
0 Kudos

Check the customer master ->sales area data->shipping tab,field value for the fields Partial delivery per item and max partial deliveries.

If this also does not help, then run program SDVBUK00 in SA38 for the sales order and check again.What is the status of the order in the document flow?