Hi,

When we trigger ATP check on STO, the order quantity is PAC and the confirmation comes back from SCM in PAC. Everything is fine for this process. But now, if we run BOP, the quantity send back to ECC is PC (which is the based unit of measure) and this is now wrong. We would like to get the same output as from the ATP check meaning we would like to get PAC again and not PC!

Is this a bug in SCM?

Let me know what you think!

Thanks

DVD

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

I think BOP results are in BUOM. Did you try using a Package size in calculation profile or rounding functionality in ECC?

http://help.sap.com/saphelp_scm70/helpdata/en/83/cd6f410eda5658e10000000a1550b0/frameset.htm