Hello Experts,
while executing the T.code CJIA (Display Project actual payment line items) I ma getting the message as " No line items were selected". and it's not displaying any data. please suggest some solutions.
Regards,
Channa
Hello Channa,
If you use project cash management, then With F-48 you should get a WRTTP 61 entry in COFP, which would lead to the entry in report CJIA. Normally the following process are applied for project cash management:
F-47 down payment request -> WRTTP 58
F-48 payment of down payment request -> WRTTP 61
FB60 or MIGO + MIRO Invoice -> WRTTP 54
F-54 clearing of down payment -> WRTTP 63, 61 and 54
F-53 payment of rest
CJFN -> WRTTP 54 gets 57
You can use CJIA after each step to check the changes.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Best to
- review the selection criteria
- verify your authorizations, you can use SU53 to analyze the authorization object
Phil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.