on 04-11-2012 5:45 PM
we have existing sap erp system and it works well now. we created new additional plant and new material for this new plant. I also created a new customer and tried making a sales order and I got this error:
"Date xx/xx/2012 lies after the end of factory calendar"
cannot find the source of the issue. I checked the customer master, material master. please help me to figure out. thanks.
This has been answered in the forum before, so please search the forum or web to find the reason before posting in the forum.
Check the calendar assigned to the plant you have created in t.code OX10. Then use t.code SCAL, select the factory calendar and click on the the change/details. Extend the To period to future year for example 2020. Then save. Note that you have do this in development system and then need to move to test and production system.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.