Cost vs Period:S-Curve

former_member195427
Active Contributor
0 Kudos

Hello Experts,

               TO view the S-curve I ran Cn41. Selected the PD or WBS. Now, when I go to menu bar as : Goto->period breakdown.....

I found this field "period breakdown" in disable mode. Please tell how can i make it into Enable mode..

Regards

Ankur

Accepted Solutions (1)

Accepted Solutions (1)

former_member195427
Active Contributor
0 Kudos

This message was moderated.

0 Kudos

Hi Ankur,

I hope you are executing steps correctly, can you check with different project in cn41,and try to upload screen shot.

Thanks

former_member195427
Active Contributor
0 Kudos
former_member195427
Active Contributor
0 Kudos

Hi!!

Thanks for your prompt reply .

I checked with different proj. also but no gain.. I have attached the screen shot .. please check..

Thanks & Regards

0 Kudos

Hi Ankur,

After placing the project definition, we need execute the TCode,then you can see Period breakdown option as enable.

Thanks

former_member195427
Active Contributor
0 Kudos

Thanks a lot GP..

Answers (0)