Hi ,

The inspection lot is created manually with inspection lot origin 89 and batch assigned manually , this batch is already assigned to inspection lot 04 and usage decision is made for that and the batch status is unrestricted

For tracking for we are assigning the same batch in inspection lot created with lot origin 89

If the characteritsics everything accepted then system allowing to perform UD , but when few of the characteristics is rejected and QN is created then system not allowing to perform UD due to open charecteristics notifcation are still present

Is that possible to skip the conditional check if the notification open can we complete the usage decision

Accepted Solutions (1)

Accepted Solutions (1)

anand_rao3
Active Contributor
0 Kudos

Gopi,

As per my knowledge quality notification status does not interfere in giving UD. There must be the open characteristics which have not been locked up to status 5. Close those characteristics and proceed for UD.

What exact error message you are getting?