on 04-10-2012 2:31 AM
Dear Experts,
We are configuring MM-SUS scenario for service procurement with service hierarchy.
Our environment is SRM 7.01/ECC6 enhpk 5. We have released purchase order from MM system with the indicator 'PO acknowledgement required'. Once the PO is released to SUS system, the SUS supplier confirms the service PO from SUS portal. However, the idoc message for PO acknowledgement is failing in the MM side. The corresponding XML message from SUS system has been successfully processed. As a result, I donot see PO acknowledgement document getting updated in the PO.
However, in case of material PO, the PO acknowledgment is working perfectly.
is it the system limitation that the PO acknowledgement is not supported for service PO with hierarchy?
Thanks and regards,
Ranjan'
Ranjan Sutradhar
Hi Ranjan,
Please refer OSS Note. 1578630 to resolve the issue.
Best Regards
RBEI SRM/Ram