on 04-07-2012 5:36 PM
Hi experts,
I'm doing some tests and I have created a new project.
I also created a a sales order with an item with special stock indicator Q, so I assigned a WBSE from the project to it.
I can see in MD04 the requirement under the WBS as Project Stock but when I run the MRP is not creating a Planned Order (as it does with the same material when the requirement is out the project).
Do you know what settings I should do in order to have planned orders generated for Project Stock requirements too?
Thanks for your help.
Fortian
please plan the material in the project network and run project MRP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Abdul Khader,
I have planned the material (one unit) in the project network (reservation for a WBS) but now the MRP is creating me a planned order with quantity 2: one for the reservation and one for the sales order.
What am I doing wrong? I guess I might not be making a correct approach... any idea?
Thanks Mahendra Dighe I would have a look to planning strategies as I am not familiar to them.
But do you know if it's possible to the MRP to take into consideration the sales order requirement even though there are no reservations at the network? (as I try to ask at the beginning of the thread).
Regards,
Fortian