Hi Guru's,
I have created a project definition intially with WBS elements structure.
Then i have planned the cost against WBS elements using ECP.
Then i have maintained the POC measurement method as Cost Prop.
after that i have run CNE1 and i am able to get the BCWS values against each WBS elements in CNE5.
Now the schenario i am trying with activities.
i just created a network and activities with work and duration (Cost is not planned on activities and it is planned on WBS elements)
After that i maintaining the POC measurement methods as Cost Prop (planned) and Work (Actual) for activites and i have not maintained any POC measurement method for WBS elements.
After doing this i have run the CNE1 and CNE5 but i am not getting BCWS values against activities.
Please help me guru's on this.
Regards,
rao
Hi Guru's,
Please provide me your valuable suggestions on this issue.
Thanks & Regards,
rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi guru's,
Please tell me one thing, if i plan costs at wbs level and maintaining activities for scheduling purpose only. In that case can i get EVA at activity level?
Please clarify me.
Regards,
rao.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.