What are the minimum tool requirements needed to use Solution Manager's BPCA?
Hi Michael,
You can use BPCA with SP level 21 on Solution Manager. The only
thing you are missing out is TBOM recording via SAP TAO and the
change impact analysis for planned Business Function activations, as
these features were shipped with higher SPs of Solution Manager.
Note 1316524 recommends the highest ST-PI level, as this would
automatically contain all bug fixes. But with Solution Manager
701 you can also use ST-PI SP03.
Kind regards,
Roland
Message was edited by: Roland Hennessy