Dear PS Experts,
I am basically an SD Consultant, but learning PS and solving issues for a client who has implemented PS module. I have an issue while cancelling an invoice. Accounting document is not getting generated. It is giving an error message as below.
Message no. BP603
Budget was exceeded by 1,210,838.00 INR in document item 1003 WBS element S.00000068-00014.
Checked with the client, he is telling budget is not exceeded. Kindly let me know if there any setting has been missed out.
Thanks and Regards
Adithya
Hi Adhithya,
If budget has not been originally exceeded, then this error usually occur due to some budget inconsistencies. I also faced the same issue.
Please follow these steps to get rid from this error:
RKANBU01 – This will correct incorrect commitment data (Related SAP note # 534993)
RKACOR04 - Fixes inconsistency between Totals & Line items (Note: 21649)
After running the above reports please run CJEN and CJBN in sequence to correct AVAC error.
Object number of a WBS element can be obtained from PRPS table.
Please let us know in case of any concerns
Thanks,
Inder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Adithya,
I have a comment in addtion to solution provided by Tushar. Please check if your goods receipt amount is higher than the invoice amount. This is likely caused the BP603.
I also found SAP note 1424698 is very useful to answer your enquiry.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check the report S_ALR_87013558. Here you can get details of Available Budget, commitments and Actuals.
Regards
Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rao,
It is not appropriate to use your mentioned report S_ALR_87013558 to check for availability control. You may see SAP note 1414563 which provides detail explanation as of why. Therefore, you may use transaction CJ30 to check the budgeted amount and whether the assigned value is available for your postings.
Regards, Gordon
Dear Gordon,
What I also want to understand is, is the budget amount related to sales invoices also. Is it not that budget amount will be applicable during procurement. As per the CJ30 Transaction, in fact the budget amount had been exceeded. Kindly request you to throw more light on this.
In fact, we have suggested to the client to increase the budget amount and waiting for their reply.
Thanks and Regards
Adithya
Dear Adithya,
I think you must have assigned the CO object (in your case WBS element) in your Sale invoices process whereby the error BP603 is trigerred. Since the assigned value is exceeded the budgeted amount in CJ30, I would recommend you to review SAP note 1424698. It explains why the availbility control is not responding as expected.
Regards, Gordon
Hi,
Check what are the settings maintained in Tolerance limit for Budget profile of your Project.
SPRO- Project System - Costs - Budget - Define Tolerance limits
Under Act. if it is maintained as 3 which is relevant for error, check what is the percentage maintained in Usage.
The "usage" represents the ratio of funds commitments to the budget, expressed as a percentage.
If this value is exceeded because of budget reductions or funds commitments which are too high, the specified action is triggered. Hence this error is coming.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.